EPSCoR - Montana NSF

MONTANA NORTHERN TIER NETWORK (C2)
circle photo circle photo
Highlights of 2009 – 2010 include:

  • MT-NTN projects have been underway since the grant’s inception, September 1, 2010
  • The table below sets out the various milestones to be accomplished during this two–year award


PROJECT MILESTONES 2009 - 2010

Designing and building the network extension in Billings

85% complete

Designing and building the network extension in Miles City

35% complete

Designing and building the network extension to Pablo and Kalispell

90% complete

Designing and implementing the upgrade to the MUS network touch point at The University of Montana-Missoula

80% complete

Preparing for future interfaces with other community anchor entities and/or neighboring EPSCoR jurisdictions

45% complete

Assessing the impact of the project (a prerequisite of assessment is having the new network segments live)

0% complete